Broadband/phone signal for Combe Martin
CMCCT have not yet set up a Working Party to progress this Project, due largely to lack of appropriate resources. As other projects are completed, we hope thereafter to commence this one.
Project title & strategic priorities
Broadband/ phone signal
SP 2, 6
Description & rationale
Poor broadband and phone signal was widely identified as a serious issue for Combe Martin. CMCCT will enter discussions with existing providers, investigate potential methods for improvement and proceed to implementation.
What it will deliver
Improved communication facilities
Who will lead & key partners
CMCCT, Business partner, DCC, ENPA
Estimated cost
£10,000
Resources required to deliver
Working group. Professional input. Negotiations with provider companies.
Next steps & dates
Form working group from within CMCCT by May 2017. Commence work programme by June 2017. Improved service by June 2018.